Completed Projects

CEDARBROOK MIDDLE SCHOOL
You are here:
BFW provided critical path scheduling and project control services for the $40 million Cedarbrook Middle School project in the Cheltenham School District of Pennsylvania. The project involved the preparation of a baseline schedule of over 1,000 schedule items among four separate prime contractors.

 

The prime contractors at various times faced delays causing the schedule to be updated regularly over 30 months. Schedule items were tracked per prime contractor to determine the cause of schedule delays. Monthly schedule updates were performed, and revised schedules were distributed to all prime contractors as well as the District Administration. The schedule was used as a tool in predetermining and addressing problems as they arose. The project was completed and occupied in June 2018.